wrs5200dfpu hYdrauLIC roLLer sCreed • operatIon manuaL — rev. #0 (08/18/14) — page 15

transPorting anD lifting ProceDUres

LIftIng the sCreed

The following procedure and Figure 1 describe how to lift

the screed.

warnIng

never lift the screed with the power unit attached.

ALWAYS remove the power unit from the screed before

lifting or transporting.

1. Utilize a spreader bar of proper length and lifting

capacity. Secure lifting straps from both ends of the

spreader bar to each of the four (4) lift loops on the

screed. There are two (2) lift loops on the operator end

and two (2) lift loops on the engine end of the screed.

2. Connect five (5) lifting cables from the spreader bar

to the lifting hook of a crane or forklift. Ensure that the

lifting hook and chain are of appropriate lifting capacity.

3. Use crane or forklift to hoist screed onto a flatbed truck

for transporting.