Delivery, Transport and Setting Up

3.4 Transport

The test chamber can be transported in three ways:

on its own castors, for which the catch on the (front) castors must be released

with a fork-lift truck; move the forks of the truck entirely under the test chamber

on a manual pallet jack

Caution:

If the test chamber is to be transported again after it has been put into operation, for

example at a different location: First empty the freshwater and condensation water

tanks (see page 22 ).

3.5

Installation

Warning!

Never stack test chambers on top of each other. The test rig on top

could fall down and serious injury or death could occur.
Warning!

The test chamber may only be installed on the floor, and never on

tables or similar. A table could collapse, or it could fall off and seri-

ous injury or death could occur.

The installation site must be flat and must be able to reliably carry the weight of the test

chamber (see chapter 2.9 Technical data on page 17 ).
An 400 V/16 A/50 Hz power connection (CEE socket) must be available at the installation site.
The distance between the test chamber and the walls/ceiling must be at least 25 cm. The

ventilation slits of the cooling unit on the front of the appliance (see page 10 ) may not be

manipulated.
Sufficient air circulation in the vicinity of the chamber must be guaranteed at all times.

• FP

• FP

• FP

• FP

Abb. 11 Minimum clearance from walls and ceiling

Position the test chamber exactly level.
After installing, lock the front swivel castors.