19 apply power and check startup sequence, 19 apply power and check startup sequence -27 – Allied Telesis 9400 iMAP User Manual
Page 31

Data Management Cable (MGMT Port on Control Module)
Apply Power and Check Startup Sequence
1-27
Telesyn x400 - Installation Guide (Installation of ATI 9400)
1.19 Apply Power and Check Startup Sequence
1.
Turn the A and then B circuit breakers on (-).
2.
Observe that the fans should start and airflow should be begin horizontally through the unit.
3.
Observe the startup sequence on the terminal interface, which should show the following:
Note:
The startup sequence the user observes on the terminal may not exactly match the one
illustrated below. However, it should be free of any error messages.
@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@
Telesyn 6G Central Fabric Controller Boot Loader Version 3.0.g.01
Created on Thu 03/11/2004 at 9:07a
Copyright Allied Telesyn Networks, Inc., 2003
VxWorks Version 5.5 for IBM PowerPC 405GP Rev E
BSP version 1.2/2
Copyright Wind River Systems, Inc., 1984-2002
@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@
FPGA Version 1.4
Starting Telesyn Product Software Loading.
Attaching to Flash File System ... done.
/tffs/ - Volume is OK
Press any key to stop automatic loading of software image...
1 0
Automatically loading software image...
Loading from boot device 'emac'...
Active CFC or DebugIP enabled: MUX Enabled
Attached TCP/IP interface to emac0.
Attaching network interface lo0... done.
Loading... 21061184
Starting at 0x10000...