Chapter 7: Cabling the Stacking Ports

92

Cabling Switches with AT-StackXS/1.0 Transceivers

To cable the switches of the stack with AT-StackXS/1.0 transceivers,
perform the following procedure:

Warning

A transceiver can be damaged by static electricity. Be sure to
observe all standard electrostatic discharge (ESD) precautions,
such as wearing an antistatic wrist strap, to avoid damaging the
device.

1. Remove the dust plug from the S1 slot on the top switch of the stack,

as shown in Figure 50.

Figure 50. Removing the Dust Plug from the S1 Slot

2. Remove the transceiver from its shipping container and store the

packaging material in a safe location.

S2/2

8

S1

/27

26

25

CON

SO

LE

SFP+