Switch installation, Installation preparation, Rack installation – HP Storage EVA Capacity Upgrades User Manual
Page 7: Guidelines for mounting equipment in a rack, Switch leds, 2 switch installation, 2switch installation

30-10022-01 loop switch user guide
7
2
Switch Installation
Installation Preparation
After receiving the switch, perform the following steps to ensure that the switch and other contents
arrived safely.
To unpack the switch:
1.
Inspect the outer shipping container for any damage that may have occurred in shipping.
Report any sign of damage to the appropriate shipping agency.
2.
Remove the switch and cables from the shipping container; save the shipping container,
foam, and antistatic bags—returning the switch in any other container is not advised.
Make sure the following parts are included:
• 30-10022-01 switch unit
• RS-232 null-modem serial cable
• Power cable
• Self-adhesive pads (4)
3.
Inspect the switch thoroughly. If any signs of damage are present, notify a sales
representative and/or the shipping agency.
Switch Installation
The switch can be installed in a rack or placed on a desktop.
Rack Installation
Guidelines for Mounting Equipment in a Rack
When installing equipment in a rack, give careful consideration to the following factors:
•
The operating ambient temperature of rack-mounted equipment must not exceed the
maximum rated ambient temperature, which is indicated in this installation guide. (See
“Operating Conditions” on page 41
.)
•
The air flow clearances specified in this installation guide must be maintained within the rack.
(See
“Operating Conditions” on page 41
.)
•
The AC supply circuit for rack-mounted equipment must be capable of supplying the total
current specified on all the labels of the rack-mounted equipment.
•
All AC power supply connections must be properly earthed. To ensure the integrity of the
earth connection, special attention must be given to connections that are not directly
connected to the branch circuit (for example, power strips).
•
The rack-mounting hardware has been carefully selected to properly support the equipment.
Any alternate rack-mounting hardware must provide equal or superior support.
•
Plan the device installation starting from the bottom of the rack cabinet. Install the heaviest
device in the bottom of the rack cabinet.
For information on environmental requirements, see
“Operating Conditions” on page 41
Switch LEDs
The switch incorporates three sets of Light-Emitting Diodes (LEDs) to indicate Ethernet, switch, and
port status:
1.
Ethernet LEDs – two separate LEDs indicating the network connection status.
2.
System LEDs – three separate LEDs indicating the switch’s status.
3.
Port LED – one multi-colored LED per port indicating the port’s status.