Operation
5.1 Start-up and general remarks for configuration
Steps for starting up the device:
• Power up
• Selection of the measuring function
• Selection of the measuring mode
• Definition of fluff and blanket concentration
• Setting of start signal / rake guard switch
• Input of extended settings
• Calibration of concentration measurement (if necessary)
DANGER!
In order to avoid injuries or damage of the device or plant equipment the device shall only be
operated with both doors properly closed and locked. The device also has to be properly
mounted and all cable feedthrough has to be properly tightened or plugged, if unused.
WARNING!
In general, the device may only be installed, commissioned, operated and maintained by properly
trained and authorised personnel.
WARNING!
To avoid damages to the equipment please make sure that power up of the meter takes place
above 0°C / +32°F. Once power is connected, the internal heater will than keep the electronics
from freezing.
WARNING!
The device starts up / restarts automatically as soon the power is switched on.
INFORMATION!
Ensure that the sensor transportation protection is removed before starting-up the system.
INFORMATION!
To install the meter in the best way, follow the steps described below.
.book Page 36 Wednesday, April 30, 2014 1:39 PM