Use the serial connection to perform basic configuration tasks, including assigning an IP address and
network mask to the system. This information is required to manage the system using the CLI through
Telnet or the Brocade Network Advisor.

Summary of installation tasks

Follow the steps listed below to install your device. Details for each of these steps are provided on the
pages indicated.

Installation tasks

TABLE 7

Task number Task

Where to find more information

1

Ensure that the physical environment that will host the
device has the proper cabling and ventilation.

Preparing the installation site

on page

26

2

Unpack the device and all included accessories,

Items included with the ICX 6430 and
ICX 6450 devices

on page 23

3

Install the device on a desktop, or in an equipment
rack.

Installing the device

on page 26

4

Once the device is installed, plug the device into a
nearby power source that adheres to the regulatory
requirements outlined in this manual.

Powering on the system

on page 45

Installation precautions

Follow all precautions when installing a device.

General precautions

DANGER

All fiber-optic interfaces use Class 1 lasers.

CAUTION

Do not install the device in an environment where the operating ambient temperature might
exceed 40 ο C (104 ο F).

CAUTION

Make sure the airflow around the front, sides, and back of the device is not restricted.

Summary of installation tasks