beautypg.com

Installation – Teledyne LGA-3500 - Laser Gas Analysis system User Manual

Page 25

background image

Laser Gas Analyzer

Installation

Teledyne

Analytical

Instruments

11

Installation

Installation of the Model 3500 includes:

Unpacking

Mounting

Flange connections

Installing transmitter and receiver

Electrical connections

Optical transmission adjustments and fine tuning

3.1 Unpacking the Instrument

The unit is shipped with all the materials you need to install and

prepare the system for operation. Carefully unpack the analyzer and inspect
it for damage. Immediately report any damage to the shipping agent.

3.2 Installation Preparation

It is very important to prepare thoroughly before installing the

system. This includes having all the tools needed handy, choosing a
proper installation location, and correct welding of the flanges to the gas
flow pipe well. See section 3.3.1. Figure 3-1 shows the general layout of
the Model 3500 Laser Gas Analyzer.

3.2.1 Installation and Adjustment Tools

The following tools will be required for proper installation:

Wrenches

M5 wrench—used to tighten the M5 bolts
connecting the instrument flange and
transmitter/receiver.

Two 12” adjustable wrenches—used to tighten
EMC and nut connector.