23
Attaching the cables
Introduction
After you turn on the analyzer and set the
TEST BATTERY
option, you are ready to test. To start testing
at a site, you need to attach the clamp or probe cables to the first jar in the site.
Note:
The figures in this section show probes connecting to the jar posts or
straps. However, you can connect the clamps in the same positions.
General rules
You should follow these guidelines when testing a jar:
•
Do not place probes or clamps on stainless steel hardware, such as bolt heads,
washers, or threaded posts. Stainless steel hardware can yield low conductance
values. If you have to test on stainless steel, record it in your testing records.
•
The jars might have grease on the terminals and connections to prevent
corrosion. You do not have to wipe off the grease before connecting the probes
or attaching the clamps.
•
Test each jar in the same location or position. Changing the location of the test
point might vary test results.
Attaching the cable to jar posts
To attach the cable to the jar:
1. Press the black probe tip against the black (–) terminal. Refer to Figure 5.
Figure 5. Attaching the cable to jar posts
2. Press the red probe tip against the red (+) terminal.