23 

Attaching the cables

Introduction
After you turn on the analyzer and set the

TEST BATTERY

option, you are ready to test. To start testing

at a site, you need to attach the clamp or probe cables to the first jar in the site.

Note:

The figures in this section show probes connecting to the jar posts or

straps. However, you can connect the clamps in the same positions.

General rules
You should follow these guidelines when testing a jar:

Do not place probes or clamps on stainless steel hardware, such as bolt heads,

washers, or threaded posts. Stainless steel hardware can yield low conductance

values. If you have to test on stainless steel, record it in your testing records.

The jars might have grease on the terminals and connections to prevent

corrosion. You do not have to wipe off the grease before connecting the probes

or attaching the clamps.

Test each jar in the same location or position. Changing the location of the test

point might vary test results.

Attaching the cable to jar posts
To attach the cable to the jar:

1. Press the black probe tip against the black (–) terminal. Refer to Figure 5.

Figure 5. Attaching the cable to jar posts

2. Press the red probe tip against the red (+) terminal.