044-001-C0-00, Rev. C

Fig. 4-10, Typical Site Arrangement, (stand-alone cabinet)

4.0

Site Preparation, continued
4.4

Site Configuration, continued

Figure 4-10 (below) shows the cable conduit route into the back of the enclosure.

Verify the conduit is trimmed 1" to 2" above the pad surface (for side chamber), or 1" to 4" for riser.

NOTE:

PRE-CAST PAD

E

B

A

D

B

A

C

C

D

E

Back

Front

Precast Polymer Pad

Compacted Gravel (12" depth recommended

Level Grade

Area of Backfilled Soil