PoleVault Systems Installation • Installation — Stage 1

2-5

Installation — Stage One, cont’d

4. Cut the ceiling tile

a.

Mark the location of the PCM 340 on the T-frame. This

aids putting it back in the correct location when the tile is

replaced.

T

Mark the screen direction on back of the tile (e.g. with

an arrow or “to front”) to help orientation of tile when
replacing it after cutting.

b.

Measure the distances X and Y (see figure) from the inner

vertical section of the front and left T-frame runners to

the center of the Pipe Adapter Plate.

c.

Using the X and Y dimensions, mark and cut a hole for

the slotted pipe in the ceiling tile.

T

Place the tile on a box and mark the hole’s center on

the underside of the tile. Use a hole saw bit to start to
cut the hole by hand (turning bit counter clockwise) to
avoid damaging the tile. When the drill bit is through
the tile, turn the tile over and finish cutting from the
top side.

5. Preliminary safety hardware installation

a

. Mark and drill holes at 10 degrees out from vertical for

each turnbuckle. Drill a fifth hole directly centered above

the PCM 340 for the safety cable.

b.

Install an appropriate anchors or lag eye bolt for the

structural ceiling into each drilled hole.

T-bar

X"

Y"

Minimum and
Maximum
Throw Distance Marks

4b

Take measurements with the PCM 340

on the T-frame

4c

Mark and start cutting the hole on the

underside. Finish on the top side.

Underside of Tile

Top Side of Tile

5a

Mark structural ceiling for lag eye

bolt installation