12 PREPARATION
FOR
INSTALLATION
Select the optimal sampling point in accordance with the generally applicable guidelines or
consult the competent persons.
Locate the sampling point in such a way that there is adequate space for inserting and
removing the probe and pay attention to the insertion length of the probe tube.
Make certain that the probe is easily accessible so that you can carry out any subsequent
maintenance work without trouble.
Locate the probe connections in such a way that the connections' temperature is always above
the acid dew point in order to avoid corrosion and blockage problems. If this is not possible, a
heated SP35/SP30 probe tube is recommended for cold connections.
If the ambient temperature in the area of the connections is >80°C as a result of radiated heat,
a radiated-heat deflector must be mounted to protect the probe.
The connection's mounting flange connection should comply with DN65 PN6. If other
connection sizes are required, a special adapter flange /S010 can be supplied as an option.
Before mounting, the probe must be adapted to the existing operating conditions.
The existing operational parameters are to be checked accordingly prior to commencing mounting
work:
weatherproof mounting position
_____present _____set
Under / over pressure situation
mbar bar
Process temperature
°C, Min. °C, Max.
Dust loading
g/m³
Dust composition - grain size
µm
Gas composition
corrosive toxic explosive
Which parameters should be
measured, e.g. O
2
, CO, SO
2
, NO
X
,..,
Vol.% mg/Nm³ ppm
Required amount of gas
l/hr,
Min.
l/hr,
Max.
Necessary T
90
time
sec.
13 MOUNTING
M&C
SP180-H probes are designed for stationary use and if properly selected and mounted a long
service life and minimum maintenance are guaranteed. It is advisable to mount the probe in an
operational position which is at a 10% inclination to the process. See also Figure 2 for the following
description.
Screw either the probe tube directly into the ¾" inner thread in the flange of the probe with
the ¾" flat gasket and tighten.
For mounting of the SP180-H at the sampling flange loosen the metal clamp around the heat
insulating protection cover and remove the cover .
If the probe connection does not correspond to the standard flange connection DN65 PN6, an
optionally supplied adapter flange should be mounted to the probe (see Figure 2).
If the heated probe tube type SP30/35 is used then the probe is to be screwed to its flange
(with welded threaded bolt). First insert the flange seal between the two flanges.
Attach the flange seal to the probe connection.
Insert mounted probe tube into the connection piece and fasten the probe using the screws
and nuts supplied.