Gas sampling and gas conditioning technology
6-5.1.1-ME
14
STARTING
W A R N I N G !
Before starting up the equipment, please ensure that the supply
voltage is identical with the information provided on the type plate.
Before starting up check whether the mains power supply voltage corresponds with the information
stated on the valves type plate.
Switch on mains power supply.
The total heating-up time is approximately 30 min. The heated 3-way-valves type V3/2-
H… and
MV3/2-H are then ready for operation
15
MAINTENANCE
No special maintenance necessary.
16
SPARE PART LIST
Wear, tear and replacement part requirements depend on specific operating conditions.
The recommended quantities are based on experience and they are not binding.
Heated 3-way-valves type V3/2-
H… and MV3/2-H
(C) Consumable parts
(R) Recommended spare parts
(S) Spare parts
Recommended quantity being in
operation [years]
Part No.
Indication
C/R/S
1
2
3
90 F 3000
Cartridge heater HLPSR, 100mm, 230VAC/350W
R
1
1
1
90 F 3010
Cartridge heater HLPSR, 100mm, 115VAC/350W
R
1
1
1
90 F 5020
Thermostat (0-180°C) for FT-
…-H2
R
1
1
1