SMA Solar Technology AG

3  Initial Setup and Start

Installation Guide

STP60-10-IA-xx-10

37

Figure 3.9 LCS tool - List of all inverters connected to the

SMA Inverter Manager

10. If sufficient PV power is present and the grid code

conditions are met, the inverters are connected to the
grid.

11. Upon commissioning, it is possible to download a

commissioning report under the menu "Reports". The
report contains information about inverter settings,
including actual disconnection values for each inverter.
See figure 3.10.

Figure 3.10 LCS tool - Commissioning report