5 installation sequence – SMA STP 60-US-10 Installation User Manual
Page 19

SMA Solar Technology AG
1 Introduction
Installation Guide
STP60-10-IA-xx-10
19
1.5 Installation Sequence
1. Pay special attention to the important safety
information at the beginning of this manual.
2. Mount the inverter according to Section 2.1, page 21,
Section 2.2, page 22, Section 2.3, page 23.
3. Open the inverter in accordance with Section 2.5,
4. Install the AC supply in accordance with Section 2.6,
5. Install Ethernet in accordance with Section 5.8,
6. Install the PV module in accordance with Section 2.9,
page 27 using a PV array junction box.
7. Close the inverter in accordance with Section 2.5,
8. Turn on AC.
9. Finalize commissioning by using the Local
Commissioning and Service Tool (LCS tool). The tool is
available from the download area at
www.SMA-Solar.com. The hardware requirements for
the LCS tool are:
– PC with Windows
TM
7 and later
– 1 GB HDD
– 2 GB RAM
The LCS tool must be installed on a local PC drive. The
PC must be connected to the system network of the
SMA Inverter Manager. For setup via the LCS tool,
refer to Section 3.3, page 31.
10. Switch on the PV system via the PV load-break switch.
11. Verify the installation by:
– Inverter display: LED "On" is permanently green.
– LCS tool: In the inverter view, the status is "On
grid".
12. The inverter is in operation now.