Installing the l1000-a, Confirming installation preparations – H3C Technologies H3C SecPath L1000-A Load Balancer User Manual
Page 17
9
Installing the L1000-A
IMPORTANT:
Keep the packages of the L1000-A and the components for future use.
Figure 3 L1000-A installation flow
Confirming installation preparations
Before you install the L1000-A, verify that:
•
You have read "
" carefully and the installation site meets all the
requirements.
•
A 19-inch rack is ready for use.
•
The rack is sturdy and securely grounded.
•
There is sufficient clearance around the rack for heat dissipation and installation.
•
No debris exists inside or around the rack.
•
Choose a correct rack mounting position for the L1000-A. Make sure the heaviest device is placed
at the bottom of the rack.