Complete the Installation

After the utilities and refrigeration connections have

been made, secure the unit to the dispenser or bin

top.

Secure ice making section to dispenser or bin

adapter.

Use strap/clips to secure unit. On some bins or

dispensers it may be necessary to drill small holes

and use field supplied sheet metal screws to secure

the ice making head to that bin, dispenser or adapter.

If the ice maker & bin or dispenser is not yet in its final

position gently move it there.

Note: The refrigerant lines above the machine must

be able to move freely while the machine is being

moved into position.

Final Check List Before Initial Start Up
1. Confirm that the ice making section is installed

indoors in a controlled environment.

2. Confirm that all packing materials have been

removed from all products.

3. Confirm that the ice making section is level.

4. Confirm that all the refrigerant connections have

been made and checked for leaks.

5. Confirm that the proper power supply has been

turned on to the condensing unit.

6. Confirm that cold, potable water has been supplied

to the ice making section and checked for leaks.

7. Confirm that the water supply is adequate.

8. Confirm that there is adequate water pressure and

that any water filters have been checked to confirm

that the cartridges do not need changing.

9. Confirm that the proper size drain tubing has been

installed and properly routed.

10. Confirm that the ice making section has been

connected to the proper power supply.

11. Confirm that the interconnecting wire has been

routed and connected between the ice making section

and the condensing unit.