SECTiON 2

INSTALLATION

if the installation will use the supplied gas hose, be sure that

the 1/2" to 3/4" gas line fitting is attached. Refer to the

instructions in the gas hose package. One gas line connection
method is shown in Figure 2-12; however, compliance with

the applicable standards and regulations is mandatory.

Inlet and regulated gas pressures can be measured using

a “U” tube manometer at the tap locations shown in Figures
2-12 and 2-13.

1.

a.

b.

Checking the Gas Supply (Inlet) Pressure

With the main gas supply valve closed and the circuit

breaker/fused disconnect in the OFF ("O") position, open

the inlet pressure tap shown in Figure 2-16 and attach a

manometer to the tap.

Depress the safety switches to allow the oven to operate,

c.

Open the main gas supply valve. Switch the circuit

breaker/fused disconnect to the ON ("I") position.

d.

Start the oven according the directions in the Operation

section of this Manual. Adjust the temperature controller
to the maximum setting (316X).

e.

Measure the supply (inlet) pressure.

f.

Switch the oven off. Close the main gas supply valve, and

switch the circuit breaker/fused disconnect to the OFF

("O") position. Remove the manometer, and close the

inlet tap.

g.

Compare the measured supply (inlet) pressure to the

nominal pressures shown In Table 1-5 (in the Description

section of this Manual).

If the supply pressure is lower or higher than the nominal

pressure, the reason should be investigated and the gas

supplier contacted.

For natural gas ovens, if the measured supply pressure is
lower than 0.247psi, or higher than 0.363psi, contact the gas

supplier. DO NOT OPERATE THE OVEN or adjust the oven
controls.