Te s t i n g T h e I n s t a l l a t i o n
(continued)
4
Press the START button.
If everything is installed correctly:
•
The green light on the start button will illuminate.
•
The process and regeneration blowers turn on.
•
The process and regeneration heaters turn on.
•
If the desiccant tanks are not in their correct position, the carousel will
turn clockwise and stop in the correct position.
5
Press the
STOP
button.
If everything is installed correctly:
•
The blowers will continue running as needed to cool the heaters.
6
The test is over. If the dryer performed the normal operating sequences as out-
lined, you can load the hopper and begin operation. If it did not, refer to the
T
ROUBLESHOOTING
section of the User Guide.
Stop
Start
3 - 1 8
l I n s t a l l a t i o n
Central
•
The regeneration heater turns on.