START-UP CHECKLIST
A. Preliminary Information
OUTDOOR: MODEL NO.
SERIAL NO.
INDOOR: AIR HANDLER MANUFACTURER
MODEL NO.
SERIAL NO.
ADDITIONAL ACCESSORIES
B. Pre-Start-Up
OUTDOOR UNIT
IS THERE ANY SHIPPING DAMAGE?
(Y/N)
IF SO, WHERE:
WILL THIS DAMAGE PREVENT UNIT START-UP?
(Y/N)
CHECK POWER SUPPLY. DOES IT AGREE WITH UNIT?
(Y/N)
HAS THE GROUND WIRE BEEN CONNECTED?
(Y/N)
HAS THE CIRCUIT PROTECTION BEEN SIZED AND INSTALLED PROPERLY?
(Y/N)
ARE THE POWER WIRES TO THE UNIT SIZED AND INSTALLED PROPERLY?
(Y/N)
HAVE COMPRESSOR HOLDDOWN BOLTS BEEN LOOSENED?
(Y/N)
CONTROLS
ARE THERMOSTAT(S) AND INDOOR FAN CONTROL WIRING
CONNECTIONS MADE AND CHECKED?
(Y/N)
ARE ALL WIRING TERMINALS (including main power supply) TIGHT?
(Y/N)
HAVE CRANKCASE HEATERS BEEN ENERGIZED FOR 24 HOURS?
(Y/N)
INDOOR UNIT
HAS WATER BEEN PLACED IN DRAIN PAN TO CONFIRM PROPER DRAINAGE?
(Y/N)
ARE PROPER AIR FILTERS IN PLACE?
(Y/N)
HAVE FAN AND MOTOR PULLEYS BEEN CHECKED FOR PROPER ALIGNMENT?
(Y/N)
DO THE FAN BELTS HAVE PROPER TENSION?
(Y/N)
PIPING
ARE LIQUID LINE SOLENOID VALVES LOCATED AT THE EVAPORATOR COILS AS REQUIRED?
(Y/N)
HAVE LEAK CHECKS BEEN MADE AT COMPRESSORS, CONDENSERS, EVAPORATORS,
TXVs (Thermostatic Expansion Valves) SOLENOID VALVES, FILTER DRIERS, AND FUSIBLE PLUGS
WITH A LEAK DETECTOR?
(Y/N)
LOCATE, REPAIR, AND REPORT ANY LEAKS.
HAVE ALL COMPRESSOR SERVICE VALVES BEEN FULLY OPENED (BACKSEATED)?
(Y/N)
ARE THE COMPRESSOR OIL SIGHT GLASSES SHOWING ABOUT
1
⁄
2
FULL?
(Y/N)
CHECK VOLTAGE IMBALANCE
LINE-TO-LINE VOLTS:
AB
V
AC
V
BC
V
(AB + AC + BC)/3 = AVERAGE VOLTAGE =
V
MAXIMUM DEVIATION FROM AVERAGE VOLTAGE =
V
VOLTAGE IMBALANCE = 100 X (MAX DEVIATION)/(AVERAGE VOLTAGE) =
%
IF OVER 2% VOLTAGE IMBALANCE, DO NOT ATTEMPT TO START SYSTEM!
CALL LOCAL POWER COMPANY FOR ASSISTANCE.
CL-1