6 commissioning, 1 before initial switch-on, Commissioning – Lenze E84DGFCR User Manual
Page 26: Before initial switch-on

Communication manual 8400 motec PROFINET
Commissioning
Before initial switch-on
26
L
EDS84DMOTPNET EN 2.0 - 11/2011
6
Commissioning
During commissioning, system-related data such as motor parameters, operating
parameters, responses, and parameters for fieldbus communication are defined for the
controller. For Lenze devices, this is done via the codes.
The codes of the controller and communication are saved non-volatilely as a data set in the
memory module.
In addition to codes for the configuration, there are codes for diagnosing and monitoring
the nodes.
The data from the controller or the memory module can only be read with the main voltage
supply (400/500 V AC).
For commissioning with 24 V DC, only the data of the digital and analog inputs in the last
two data words are valid and readable (see
Process input data AI/DI (Slot2)
).
6.1
Before initial switch-on
Stop!
Before you switch on the controller for the first time, check the entire wiring for
completeness, short circuit, and earth fault.