It1000-ab, Maintenance, Preventative maintenance schedule – BAND-IT IT1000-AB 1/4 Tie-Lok Tool User Manual
Page 21: 21 of 38, 1/4” tie-lok, Tool
Document # I17791 Rev H
© Copyright
BAND-IT-IDEX, Inc. 2009
All rights reserved
www.BAND-IT-IDEX.com
BAND-IT-IDEX, Inc.
A Unit of IDEX Corporation
4799 Dahlia Street Denver, CO 80216-0307 USA
P: 1-800-525-0758 F: 1-800-624-3925
21 of 38
IT1000-AB
1/4” Tie-Lok
®
Tool
Replace Gripper
Front Gripper
Replace Assembly
Tension Block Assembly
Clean & Re-Lubricate
Front Gripper
Rotate
Cut-off Blade
Clean & Re-Lubricate
Tool Head
Clean & Re-Lubricate
Flip Cover
Clean & Re-Lubricate
Tension Block Assembly
Every 12,500
Maintenance
Action
Maintenance
Item
Clamps
Installed
Replace
Blade, Blade pin, Knife
and Knife pin
Every 50,000
Rotate
Cut-off Knife
Clean & Re-Lubricate
Mechanical Linkage
Every 25,000
Preventative Maintenance Schedule
Tool Preventative Maintenance:
The tool has some wear components that must be checked and replaced on a certain
schedule. BAND-IT has developed a Preventative Maintenance (PM) schedule to help
facilitate these requirements. If tools are experiencing difficulties during function or there
audible air leaks coming from inside the handle, the tool should be returned to BAND-IT-
IDEX, Inc. for servicing.
BAND-IT recommends that the tool be sent in for general overhaul every 100,000 clamps
installed.