Roof sHeeTInG seQUence
It is recommended that both sides of the ridge of a building be sheeted simultaneously . This will
keep the insulation covered for the maximum amount of time and the panel ribs can be kept in
proper alignment for the ridge panel . Check for proper coverage as the sheeting progresses .
note
panel-sheeting sequence below.
5
6
7
8
9
10
11
12
1
2
3
4
noTe: If slippery substances are present on the roof panels wipe them clean
immediately to prevent slipping or falling. Workers should maintain a constant
awareness of their location relative to the roof edge.