Input/Output Wiring – Dual Mains

The UPS is designed for single mains installation as default. Follow the below instructions to install
the UPS in a dual-mains installation

Wiring procedure – dual mains

 Loosen the (6) M4 screws from the cover of the cable termination area, and remove.

 Loosen the (2) M4 screws (1 each side) from the top part of the Conduit Box. Loosen the M4

screws attaching it to the bottom part (2 screws in a 13.8 5in/352 mm Enclosure, 3 screws in a
20.59 in/523 mm Enclosure), and remove.

 Loosen the (4) M4 screws (2 each side) from the bottom part of the Conduit Box and remove.

Note

The illustrations show 20.59 in/523 mm Enclosures, but the installation procedures are
identical for 13.85 in/352 mm Enclosures).

N

A

B

C

N

By

pass

O

ut

put

Input

Conduit box
(top part)

Conduit box
(bottom part)

EPO Conduit

MBP Conduit

This manual is related to the following products: