beautypg.com

HP Virtual Connect Enterprise Manager Software User Manual

Page 42

background image

IMPORTANT:

For more information on the domain, network, and storage configurations that VCEM can

replicate during completion of VC Domain Maintenance, or discard in case of a failure or cancellation of
the VC Domain Maintenance operation, see

VC Domain Group configuration replicated to other VC Domains

during VC Domain Maintenance

.

To cancel a VC Domain Maintenance from the VC Domain page:

1.

Select the VC Domain with status under maintenance.

2.

Click VC Domain Maintenance. The VC Domain Maintenance page appears.

3.

Click Cancel. The Virtual Connect Enterprise Manager is executing the request
message is appears with a job ID code.

4.

Click OK to go to the Jobs page and monitor job progress.

Resynchronizing a VC Domain with Configuration Mismatch

Resynchronize a VC Domain is a useful way to force VCEM to verify that the VC Domain is still compatible
with VC Domain Group configuration without removing and adding that VC Domain to a VC Domain Group.
The VC Domain configuration must comply with the same requirements when you add a VC Domain into a
VC Domain Group for the first time.

To resynchronize a VC Domain:

1.

Go to the VC Domains tab.

2.

Select the VC Domain with Configuration Mismatch status.

3.

Click VC Domain Maintenance. A dialog box showing the VC Domain to be resynchronized appears.

4.

Click OK to confirm. The Virtual Connect Enterprise Manager is executing the
request

message appears with a job ID code.

5.

Click OK to go to the Jobs page and monitor job progress.

42

Managing VC Domains