Check of setpoint display

1)

Switch on power source, allow at least 15 minutes’ warm-up time.

.

2)

Set switch D (front panel of GS 8A) to “0” position.

3)

Adjust zero to 0 or 4 mA with the 10-turn potentiometer P (front panel of GS 8A),
depending on setting in Fct. 1.05, deviation <±10 µA.

4)

Calculate position of switch Y and displayed setpoints ”I“ and ”f“:

4.1)

X =

Q

100%

x

K

GK

x

DN

2

Q

100%

full-scale range (100%) in volumetric unit V per unit time t

GK

primary constant, see instrument nameplate

DN

meter size DN im mm, not inches, see instrument nameplate

t

time in seconds (Sec), minutes (min) or hours (hr)

V

volumetric unit

K

constant, according to following table

t

Sec

min

hr

V
Liter

25 464

424.4

7.074

m3

25 464 800

424 413

7 074

US gallons

96 396

1 607

26.78

4.2)

Determine position of switch Y: Use table (front panel GS 8A) to determine value Y
which comes closest to factor X and meets condition Y

X.

4.3)

Calculate setpoint reading ”I“ for current output:

I = I

0%

+ Y (I

100%

- I

0%

) in mA

X

I

0%

current (0/4mA) at 0% flowrate

I

100%

current (20mA) at 100% flowrate

4.4)

Calculate setpoint reading ”f“ for pulse output:

f = Y

x

P

100%

in Hz

X

P

100%

pulses per second (Hz)
at 100% flowrate

5)

Set switch D (front panel GS 8A) to position “+“ or “-“ (forward / reverse flow).

6)

Set switch Y (front panel GS 8A) to the value determined by the method described above.

7)

Check setpoint readings I and f, see points 4.3 and 4.4 above.

8)

Deviation <1.5% of setpoint. If greater, replace signal converter, see Sect. 8.4.

9)

Test of linearity: set lower Y values, readings will drop in proportion to the calculated Y
values.

10)

Switch off power source after completing the test.

11)

Disconnect the GS 8A.

12)

Reassemble in reverse order, see points e) – b) under “electrical connection”,
see illustration in Sect. 8.5.

13)

The system is ready for operation after the power source has been switched on.

Example: see overleaf

Note:
Sticker on the GS 8 A primary head simulator still gives values for
“inch” flowmeter. Do not use any more !