4.2 Preliminary Power-Off Check List
Make the following checks of the installation before proceeding
further into the start-up procedure:
1. Check to see that the sample and supporting gas installation is in
accordance with the specifications called for in the installation
and application sections of the manual (Chapter 3). Be sure that
the supporting gases are of the proper composition and are
connected to the correct fittings at the rear of the analyzer.
2. Check to see that the electrical installation conforms to the
instructions contained in the installation section (Chapter 3) and
on the input-output diagram.
3. Remove the top cover and check to see that the printed circuit
boards and cables are firmly seated in their respective sockets.
4. Confirm that recorder and alarm connections are properly made.
4.3 Powering Up the Unit
Before applying power to the analyzer for the first time perform the
following checks:
1. Make sure that the proper power 120/220 VAC 50/60 Hz is
available.
2. Connect the AC power cord to the rear panel and then plug the
other end into the mains supply. As soon as power is established,
the unit will turn on.
3. Check that the Power, CPU, and COM LEDs illuminate and the
Teledyne Logo screen appears on the display.