Fulton FB-S Horizontal Firetube Boiler User Manual
Page 51

The Fulton Companies*FB-S Series Manual*Version 2010-0820 rev. 3/5/13
Page 51
Note
As well as removing sludge from the boiler, a second and equally
important function is to maintain the TDS (totally dissolved solids) level to
within the required limits. The amount of blowdown, and hence time
required, it dependent on the amount of TDS in the raw water supply, the
percentage condensate return, water treatment chemicals added and the
number of the hours a day operation. In order to establish the required
blowdown rate, consult your water treatment specialist who will
recommend a water treatment program in terms of appropriate
chemicals and the required blowdown rate, which takes these factors
into account.
Water Level Gauge Blowdown
a) Blowdown the water level gauge set by opening the gauge blowdown valve A and
closing the top and bottom gauge valves B and C in sequence.
b) On completion of the blowdown procedures, ensure all isolation valves are open,
and all blowdown valves are SHUT (all handles vertical).
5. To Shut Down the Burner
Short Term (hours)
a) Turn the burner On/Off/Reset Switch on the Burner Control Panel to OFF.
b) The burner will stop firing, post-purge and then stop.
Flame Programmer
Pressure Controller
Pressure Switches
Level Probes
Steam Stop Valve
Surface Blowdown
Connection
Level Controller
Feedwater Connection