installation guide 7

h

'2/5.$

operator installation/surface operator

Concrete must be even and leveled, avoiding any operator unbalance and unevenness.
Conduit requirements may vary depending on your specific needs. Use only sweeps for conduit bends, do
not use 90° connectors this will make wire pulls very difficult and can cause damage to wire insulation. A
suggested minimum of 3/4-inch conduit should be used. Be sure that all conduits are installed in accor-
dance with local codes.

2

/0%2!4/2

0/3)4)/.

Mix and pour concrete into the trench, al-
low the concrete to cure and place the op-
erator into position.

1

3

From the operator position dig a trench.

NOTE: The trench should enclose the con-
duits.

Run conduits from the operator to their
corrsesponding source .

1

3

•Hi Voltage Conduit
•Low Voltage Conduit
•Loop Lead Conduit
•Sequencing Control or

Primary/Secondary Conduit

2

The operator must be installed on a concrete base. Soil conditions

and local building codes will determine concrete base depth and

width.

•For added support use rebar and/or wire mesh.

•Concrete base should be even and leveled avoiding any

operator unbalance.

•Mix concrete according to manufacturer.
•Pour and tamp concrete into form.
•Level and surface.
•Allow concrete to cure for 48 hrs.