1601-065-M-05-07
installation guide 23
arm installation/wishbone
/./
.
/&&/
&
&
/./
.
/&&/
&
&
Install the inside/outside counterweight plates on the barrier
arms using the supplied hardware.
Install the two (2) barrier arm mounting brackets onto the
hubs as shown, do not tighten the bolts at this time. Refer to
page 22 for more information.
Slide the 14’ft. barrier arm through the mounting brackets.
The arms must extend at least 14” inches behind the arm
hubs allowing the counter balance plates to be installed.
Tighten and secure the 14’ ft. arm to the
arm hubs.
Install the 10’ ft. barrier arm between the two 14’ ft. arms us-
ing the supplied hardware.
3
2
1
4
5
1
2
3
4
5
Check for correct shaft rotation.
Refer to page 21 when installing the hubs.