5. Assembly
PNEG-720-G2 12" and 16" Series II Sweep
55
B. Center Pivot for Standard Sweep
NOTE: The center pivot for a standard sweep must be supplied by the customer. The following are
requirements for installation.
1. The cross braces must be 1/2" steel plate.
2. The pivot pin must be 1-1/2" diameter steel bar and extend approximately 4" above
floor elevation.
Control Panel Setup
If the meter looks like this:
Figure 5AM
Follow these instructions:
The control panel is intended for hard wired connections for power in, auger drive motor wiring,
tractor drive motor wiring and the thermal overload wiring for both the auger drive motor and the tractor
drive motor.
If the system that this control panel is designed to have the cables for the auger drive motor and the tractor
drive motor run inside the bin on the floor and exit through the bin door, a plug package is available to
allow the panel to connect to the cords without hard wiring. This package is GC20117. This package is
only standard in the center pin style sweep systems and not in the protected cord center sweep systems.
CAUTION
The pivot pin MUST be in the center of the bin. If it is not, the sweep could hit the
bin wall.