5. Assembly

44

PNEG-720-G2 12" and 16" Series II Sweep

G. Loosely bolt the bottom belt guard to the motor mount using four (4) 3/8"-16 x 1" hex bolts, flat

washers and lock washers.

(See Figure 5Z.)

Figure 5Z

H. Slide the top belt guard over the bottom belt guard as shown in

Figure 5Z

and tighten bolts.

I. Install belt guard bottom back plate.

J. Slide belt guard bottom pan and bolt into place.

Electrical Assembly

NOTE:

See chart on Page 45

for the correct size of conduit with the corresponding sweep size.

A. Place the 3/4" rigid conduits in order starting with the head section and working towards the tail or

extension section.

WARNING

All electrical wiring and service work must be performed by a qualified
electrician and must meet all State and Local Electrical Codes.