beautypg.com

Installation guide, Installation, Rs-485 connection status – Veris Industries H8036 SERIES Install User Manual

Page 3: Address, Disconnect and lock out power before installation

background image

Z201686-0N

PAGE 3

©2012 Veris Industries USA 800.354.8556 or +1.503.598.4564 / [email protected]

08122

Alta Labs, Enercept, Enspector, Hawkeye, Trustat, Veris, and the Veris ‘V’ logo are trademarks or registered trademarks of Veris Industries, L.L.C. in the USA and/or other countries.

TM

H8035/H8036

INSTALLATION GUIDE

INSTALLATION

Disconnect and lock out power before installation.

The Enercept meter, including the current transformers (CTs), voltage connection
fuses, and fuse pack, is permitted within electrical distribution equipment
including but not limited to panelboards, switchboards, motor control centers, and
transformers. Carefully review the equipment in which the Enercept meter will
be installed. Consider the following installation conditions during the installation
process:

• Review the equipment enclosure for ventilation openings. Wires will cross

many of these openings in a normal installation, however, do not install
the Enercept where it will substantially block ventilation openings in the
enclosure.

• The Enercept meter and the wiring installed within a wiring space

or gutter should not exceed 75 percent cross sectional fill at the
Enercept meter parts as addressed in the NEC. Improper installation of
Enercept meter in the wire gutter of equipment may affect the thermal
performance of the equipment.

• Consider the arrangement of CTs within the equipment to ensure the

correct bending radius of conductors.

• Review the arrangement and location of the CTs within the equipment.

Use appropriate support for the CT to prevent undue strain on the
conductor.

1. Choose a unique address and set the switches for that address as

shown in the Address Selection Switches section. Only addresses 1
to 63 can be used.

2. Connect the voltage leads to the phase conductors at a location that

is not normally turned off. Connect voltage leads on the Line side
of the conductor to ensure constant power to the Enercept. For a
3-phase system, connect the red lead to phase A, black to phase B, and yellow to
phase C. See the Wiring section on the following page.

3. Snap the CT onto the conductor.

Connect CTs to the correspondingly
colored voltage leads. If the
application can exceed 20 times the
rated CT current, use wire ties to
secure the I-bar to the CT housing.
This CT automatically detects phase
reversal, so CT load orientation is not
important.

Wire tie

RS-485

CONNECTION

STATUS

+

-

Shield

ADDRESS

1
2
4
8

16
32

4. Remove the terminal block and attach the RS-485 wires. Observe (+), (-), and

Shield polarity. Insulate any exposed wiring.

SHIELD

SHIELD

S

S

SHIELD

120

Terminator

5. For information regarding software setup, see the Modbus protocol specifications

available at www.veris.com/Modbus/.

6. Check power reading (these calculations are approximations only).

Expected power:

kW = Volts x Amps x 1.732 x PF / 1000

kW = Horsepower x 0.746