beautypg.com

Water piping — multiple zones, Gold cgi gas-fired water boiler — boiler manual, Piping multiple zones – Weil-McLain GOLD CGI 550-110-710/0107 User Manual

Page 22

background image

GOLD CGi Gas-Fired Water Boiler — Boiler Manual

Part Number 550-110-710/0107

4c

Piping multiple zones

Follow instructions on pages 0 and 1 to install near-
boiler or single-zone piping. (Also refer to

Piping for

radiant heating systems or converted gravity sys-
tems

, below, if applicable.)

See

Figure 18

or

Figure 19

to complete installation.

Zoning with circulators (Figure 18)
(return temp over 130°F)

1. Size each circulator to individual circuit require-

ments.

. Do not install circulator on boiler (except for pri-

mary/secondary piping).

3. Install isolation (balancing) valves to adjust flow to

distribute heat to all zones.

4. Install and wire a separate relay for each zone cir-

culator.

Zoning with zone valves (Figure 19)
(return temp over 130°F)

1. Install isolation (balancing) valves to adjust flow to

distribute heat to all zones.

. Provide a separate 4-volt transformer to power the

zone valves. Size the transformer to handle the total
rated load of all connected zone valves.

Piping for radiant heating

systems or converted gravity

systems

Converted gravity (or steam) systems

Whenever possible, use the primary/secondary piping
shown in

Figures 20 or 21

on page 5. This piping de-

sign allows changing boiler flow rate without affecting
primary circuit flow rate.
If

Figures 20 or 21

cannot be used, use the boiler-bypass

piping shown in

Figure 22 or Figure 23

on page .

You can also use the piping shown in

Figure 24

on

page 9 (system-bypass), if the reduced flow rate in
the heating system will not cause heat distribution
problems.

Failure to prevent low return water

temperature to the boiler could

cause corrosion of the boiler sec-

tions or burners, resulting in severe

personal injury, death or substantial

property damage.

Radiant heating systems

Preferably, use primary/secondary piping, as shown
in

Figures 20 or 21

on page 5. Alternatively, use the

method of either

Figure 22 or Figure 23

on page .

Do not use the piping of Figure 24

(system-bypass),

because this method does not control radiant system
supply temperature.
If radiant system tubing has no oxygen barrier, a

heat

exchanger

must be used.

Radiant heating system piping should include a means of regulating the boiler return water

temperature and the system supply temperature (such as provided by an injection pumping

control). Boiler return water temperature will be adequately controlled using the methods

shown in this manual provided the system supply temperature is relatively constant.

DO NOT

apply the methods in this manual if the system is equipped with an

outdoor reset

control

. Instead, provide controls and piping which can regulate the boiler return water

temperature at no less than 130°F regardless of system supply temperature. Contact your

Weil-McLain representative for suggested piping and control methods. Failure to prevent

cold return water temperature to the boiler could cause corrosion damage to the sections

or burners, resulting in possible severe personal injury, death or substantial property dam-

age.

Water piping — multiple zones