12.6 Measuring the ionization current

-

Switch off the system using the Central Heating button and the DHW button

-

Disconnect

the

plug

and

the

socket

connection on the probe and connect the

measuring device in series. See figure 23.
Select the µA direct current range on the measuring
device. The measuring device must have a resolution
of at least 1 µA.

-

Switch on the sytem using the Central Heating button
and the DHW button.

-

Press the MODE-button for 5 seconds.

-

The display will show COdE followed by an arbitrary
number;

-

Select by means of the

or the

button the code C123;

- Press the Store-button to confirm the code (code blinks 1 x);

-

Press the MODE-button until SERV is shown;

-

Press the STEP-button once until 1 is shown;

alternately 1 and OFF will be shown.

-

Press the

button until the maximum value (in kW) is achieved;

The boiler will burn on full load (value on display in kW)

value in BTU/hr = x3415

-

Measure the ionization. When the boiler is in full load the ionization current must
be > 4 µA and write down this value in the log book.

-

Press the

button until OFF is shown (keep button pressed).

-

Switch off the system using the Central Heating button and the DHW button

-

Disconnect the measuring device and restore the plug and the socket connection
on the probe.

-

Switch on the sytem using the Central Heating button and the DHW button.

12.7 Installing the casing

- Install the cover on the boiler and clos all 4 quick releases of the casing

- Tighten the 4 screws A,B,C and D in the quick releases (figure 24);

- Tighten the screw E behind the door on the front of the casing (figure 24);