69
Recording
When timer programs overlap
When 2 or more programs overlap, one having the largest
program number is executed.
Example 1)
•
Program 1: 14:00 to 17:00, 0.5 FPS for normal
recording
•
Program 2: 15:00 to 16:00, 2.0 FPS for normal
recording
These programs overlap between 15:00 and 16:00. In this
case, Program 2 takes priority and the recorder operates as
shown in the illustration below.
Example
Program 1: 14:00 to 17:00, 0.5 FPS for
normal recording
14:00
15:00
16:00
17:00
14:00
15:00
16:00
17:00
0.5 FPS
2.0 FPS
2.0 FPS
Program 2: 15:00 to 16:00, 2.0 FPS for
normal recording
Actual recording operation
0.5 FPS
0.5 FPS
Program 2
Program 1
Program 1
Example 2)
•
Program 1: 14:00 to 17:00, 0.5 FPS for normal
recording
•
Program 2: [Skip] from 15:00 to 16:00
These programs overlap between 15:00 and 16:00. In this
case, Program 2 takes priority and the recorder does not
perform recording from 15:00 to 16:00 as shown in the
illustration below.
Example
Program 1: 14:00 to 17:00, 0.5 FPS for
normal recording
14:00
15:00
16:00
17:00
14:00
15:00
16:00
17:00
0.5 FPS
Skip
Program 2: [Skip] from 15:00 to 16:00
Actual recording operation
0.5 FPS
0.5 FPS
Program 2
Not
recorded!
Program 1
Program 1