Electrical Connection

Installation Guide

SMC6-8TL-IEN101040

35

4. Check the strings for ground faults, as described in section 9.3.1 ”Checking the PV Generator

for a Ground Fault” (page 68).

5. Check the DC plug connector for correct polarity and connect it.

To release the plug connectors see section 7.2 ”Opening the Inverter” (page 52).

6. To create the sealing on the inverter, all the DC

inputs that are not needed have to be closed as
follows:
– Insert the provided sealing plugs into the

unneeded DC plug connectors.
Do not insert the sealing plugs into the DC
inputs on the inverter.

– Insert the DC plug connectors with sealing plugs

into the corresponding DC inputs on the inverter.

7. Check the Electronic Solar Switch for wear, as

described in section 8.2 ”Checking the Electronic
Solar Switch (ESS) for Wear” (page 60) and
attach it firmly.