Example: Location of the ground fault

The example shows a ground fault between the second and third PV module.

3. If a definite ground fault cannot be measured and the message is still displayed, measure the

insulation resistance.

4. Reconnect the strings without ground faults to the inverter and recommission the inverter (see

Section 11, page 61).

Test by Measuring the Insulation Resistance

If the voltage measurement does not provide sufficient evidence of a ground fault, the insulation
resistance measurement can provide more exact results.

Required devices:

☐ Suitable device for safe disconnection and short-circuiting
☐ Measuring device for insulation resistance

Procedure:

1. Calculate the expected insulation resistance per string.

2.

Danger to life due to high voltages

• Disconnect the inverter from all voltage sources (see Section 9, page 41).

3. Install the short circuit device.
4. Connect the measuring device for insulation resistance.
5. Short-circuit the first string.
6. Set the test voltage. The test voltage should be as close as possible to the maximum system

voltage of the PV modules but must not exceed it (see datasheet of the PV modules).

7. Measure the insulation resistance.
8. Eliminate the short circuit.
9. Measure the remaining strings in the same manner.

☑ If the insulation resistance of a string deviates considerably from the theoretically

calculated value, there is a ground fault present in that string.