Power Requirements

Table 1 outlines the power service requirements for various locations:

Location Volts

Hertz

Amps

United States

125

60

20

Europe / Asia

220

50

15

Japan 125

60

20

Australia / Other: Setup as
needed per site

Table 1 Power Requirements

Power Installation

The following list outlines the power installation steps:

ƒ

The customer’s electrician must run the proper voltage service with a
junction box and a standard outlet to within 2’ (0.5m) of the MCC
server installation location.

ƒ

A Visara technical representative will contact the customer two weeks
before the scheduled MCC installation to verify that the MCC power
outlet has been successfully installed.

Note: Failure to install and test the MCC power outlet will delay

the MCC installation.