Chapter 2 Site Preparation and Installation Overview
Installation Preparation Guide
17
Site Installation
Site installation activities listed below are principally the responsibility of
the customer; Visara will assist where appropriate.
Power installation (Chapter 3 Power Requirements)
Run the appropriate service to the MCC server installation location.
Cable installation.
Note: This is not a complete list, see Chapter 4 MCC Network and
Chapter 5 Connectivity Interfaces for more details.
Run coax cable from each controller (3174 or other) port to the MCC
rack installation location.
Enable the MCC’s IP address for remote client support on all HMCs.
Run network cable from the appropriate systems (or a drop from the
corporate network) to the MCC server installation location for
telnet/VT100 access.
Connect MCC to Network. Depends on network design decisions. Final
requirement is Ethernet access from each Thin Client / workstation to
the MCC server.
Install analog phone line for the modem and phone.