22). Connect the unit to the gas and electrical supply.
23). Before concluding the conversion, make sure you leak test
the entire system and check all operational functions to ensure
that the unit is performing safely and properly.
24). Fill out required information on LP conversion label.
25). Remove rating plate from under appliance and turn it over
to the blank side.
26). Apply sticker to blank side. Put rating plate back.
19). Replace the NG Pilot orifice with the LP Pilot orifice. If you
get the orifices mixed up, the LP orifice has a grove machined
around the diameter near the end.
20). Reverse steps to install pilot hood.
21). The minimum primary air setting is different depending on fuel
and burner. The minimum primary air is set by hand-bent tabs on
the primary air adjustment. Bend the appropriate tab down for your
fuel and burner. See specifications table or primary air adjustment
for proper tab. See image below for tab lengths. If your setting is
fully closed, bend both tabs up.
1/16 "
3/16 "
Figure 19 Sec.6
Figure 20 Sec.6
Figure 21 Sec.6
Figure 22 Sec.6
Figure 23 Sec.6