Ductwork connections, Rail mounting, Roof curb mounting - continued – Greenheck ERCH - Energy Recovery Unit with Packaged DX (468151) User Manual

Page 6: Curb cap details for factory supplied roof curbs

background image

6

Energy Recovery Unit with Packaged DX

1 Fan

Wheel

Dia.

1 Fan

Wheel

Dia.

Rotat

io

n

Rotat

io

n

R

ot

ation

R

ot

ation

Length of Straight Duct

GOOD

POOR

GOOD

POOR

GOOD

POOR

Turning

Vanes

Turning

Vanes

SYSTEM EFFECT FACTOR CURVES

FPM X 100

OUTLET VELOCITY

0 5 10 15 20 25 30 35 40 45

1.2

1.0

0.8

0.6

0.4

0.2

0.0

S

TA

TIC PRESSURE LOSS

CUR

VE

1

CUR

VE

2

CUR

VE

3

CUR

VE 4

1 Fan

Wheel

Dia.

1 Fan

Wheel

Dia.

Rota

tio

n

Rota

tio

n

R

ot

ation

R

ot

ation

Length of Straight Duct

GOOD

POOR

GOOD

POOR

GOOD

POOR

Turning

Vanes

Turning

Vanes

SYSTEM EFFECT FACTOR CURVES

FPM X 100

OUTLET VELOCITY

0 5 10 15 20 25 30 35 40 45

1.2

1.0

0.8

0.6

0.4

0.2

0.0

S

TA

TIC PRESSURE LOSS

CUR

VE

1

CUR

VE

2

CUR

VE

3

CUR

VE 4

DUCTWORK CONNECTIONS

Examples of good and poor fan-to-duct connections are shown below . Airflow out of the fan should be directed
straight or curve the same direction as the fan wheel rotates . Poor duct installation will result in low airflow and
other system effects .

ROOF CURB

SIDE OF UNIT

BASE

1 INCH INSULATION

E

D

C

A

B

Rail Layout
• Rails designed to handle the weight of the ERCH should be

positioned as shown on the diagram (rails by others) .

• Make sure that rail positioning does not interfere with the supply

air discharge opening or the exhaust air intake opening on the
ERCH unit . (Avoid area dimensioned “B” below) .

• Rails should run the width of the unit and extend beyond the unit

a minimum of 12 inches on each side .

• Set unit on rails.

B

A

SUPPLY/EXHAUST

OPENING

OUTDOOR AIR

INTAKE HOOD

B

A

SUPPLY/EXHAUST

OPENING

OUTDOOR AIR

INTAKE HOOD

Isometric view of unit on rails

Side view of unit on rails

RAIL MOUNTING

Model

Rail

Mounting

A

B

ERCH-20

5 .00

41 .00

ERCH-45

7 .00

41 .90

ERCH-55

5 .50

53 .00

ERCH-90

6 .00

59 .00

All dimensions shown are in inches .

Model

Curb Cap Dimensions

A

B

C

D

E

ERCH-20 2 .00

2 .00

1 .00

0 .88

0 .75

ERCH-45 2 .00

4 .25

2 .00

1 .31

0 .50

ERCH-55 2 .00

4 .25

2 .00

1 .31

0 .50

ERCH-90 2 .00

4 .25

2 .00

1 .31

0 .50

All dimensions shown are in inches .

Curb Cap Details for Factory Supplied Roof Curbs

ROOF CURB MOUNTING - CONTINUED

Recommended Discharge Duct Size and Length

Model

Blower Size

Duct Size

Straight Duct Length

ERCH-20

9

14 x 14

36

ERCH-45

12

20 x 20

48

ERCH-55

15

28 x 28

60

ERCH-90

18

32 x 32

60

All dimensions shown are in inches .

• Recommended duct sizes are based on velocities across the cfm range of each model at approximately 800 feet per minute (FPM) at

minimum airflow and up to 1600 fpm at maximum airflow . Recommended duct sizes are only intended to be a guide and may not satisfy
the requirements of the project . Refer to plans for appropriate job specific duct size and/or velocity limitations .

• Straight duct lengths were calculated based on 100% effective duct length requirements as prescribed in AMCA Publication 201.

Calculated values have been rounded up to nearest foot .