Start-up checklist for unit – Greenheck ERCH - Energy Recovery Unit with Packaged DX (468151) User Manual

Page 25

background image

25

Energy Recovery Unit with Packaged DX

Start-Up Checklist

The unit will be in operational mode during start-up . Use necessary precautions to avoid injury . All data must be
collected while the unit is running . In order to measure volts & amps, the control center door must be open, and
the unit energized using a crescent wrench to turn the disconnect handle .

Special Tools Required

• Voltage Meter (with wire probes)

• Thermometer

• Amperage Meter

• Pressure Gauges

• Incline manometer or equivalent

• Temperature Gauges capable of measuring pipe temperature

• Tachometer

START-UP CHECKLIST FOR UNIT

Pre-Start Up Checklist -

check boxes as items are completed

o

Disconnect and lock-out all power switches

o

Remove any foreign objects that are located in the energy recovery unit .

o

Check all fasteners, set-screws, and locking collars on the fans, bearings, drives, motor bases and

accessories for tightness .

o

Rotate the fan wheels and energy recovery wheels by hand and ensure no parts are rubbing . If rubbing

occurs, refer to Start-Up section for more information .

o

Check the fan belt drives for proper alignment and tension (refer to Start-Up section for more

information) .

o

Filters can load up with dirt during building construction . Replace any dirty pleated filters and clean the

aluminum mesh filters in the intake hood (refer to Routine Maintenance section) .

o

Verify that non-motorized dampers open and close properly .

o

Check the tightness of all factory wiring connections .

o

Verify control wire gauge (refer to the Electrical Connections section) .

o

Verify diameter seal settings on the energy recovery wheel (refer to Start-Up section for more

information) .

o

Verify proper drain trap installation (refer to Drain Trap section) .

o

Check condensing fans for any damage or misalignment . Spin the blades and make sure they don’t

contact any parts and are free turning without any resistance .

o

Look over the piping system . Inspect for oil at all tubing connections . Oil typically highlights a leak in

the system . If a leak is present, refer to the Maintenance section in this manual .

o

Inspect all coils within the unit . Fins may get damaged in transit or during construction . Carefully

straighten fins with a fin comb .

o

If there is an indirect gas-fired furnace in this unit, refer to the PVF IOM provided with this unit for __

Pre- Start-Up information .

o

This unit contains a crankcase heater for each compressor which needs power supplied to it 24 hours

prior to start-up . If start-up is scheduled in 24 hours, unlock the disconnect power and energize unit .

Start-Up Procedure

• Make sure Pre-Start-Up checklist is complete.
• Jumper R to G, R to Y1, and R to Y2 (if applicable) on the control board.
• Turn the disconnect on. After 3 minutes compressors will come on. Make sure all fans and compressors are

rotating the correct direction .

• Allow the unit to run until the refrigerant system stabilizes. Approximately 1-2 minutes.
• Take the following measurements while the unit is running to ensure proper operation.

WARNING!

All motor(s) / compressor(s) have been checked for rotation . If blower rotation is incorrect, wiring must be

changed at the disconnect to ensure all motor(s) / compressors are corrected .

Operation of scroll compressor(s) in this unit are directional and will be damaged if run with the wrong direction .