Installation

Page 6

MDE-4511B Retrofit Kits for Atlas™ Electro-mechanical and Commercial Electronic Units Installation Instructions · June 2011

Installation

Preparing for Installation

Before you begin, obtain permission from the manager/owner to remove power from the unit
and then remove power using normal procedures. Follow the OSHA lockout/tagout safety
procedures.

Ensure that you have the proper kit for the dispenser to be retrofitted.

1

Unlock and remove the doors from both sides of the unit using the proper key for the unit. Place
the doors in a safe place to prevent damage or scratches.

2

Remove the two screws securing the dial enclosure assembly and remove the assembly using a
cross-tip screwdriver.
Note: Retain the screws for replacing assembly after installation.

3

Remove the two screws (located above the display) at Side 1 of the unit and pull the display
cover forward using a cross-tip screwdriver. The cover will pivot down in a horizontal position
allowing access to the electronics section of the unit.
Note: Retain the screws for replacing the assembly after installation.

Installing the Pulse-out/RS-485 Board (Commercial Unit Only)

To install the Pulse-out/RS-485 Board, proceed as follows:

1

Locate the correct board for your application in the kit. The board type in your kit is determined
as follows:

• M06382K003 kit has the RS-485 Board (M06725A001) (New Bezel with Totalizer opening

may be required).

• M06382K004 kit has the Pulse-out Board (M06587A001).

Note: For description of kits, refer to

“Introduction”

on

page 1

.

2

Connect the new board P2 Connector to P8 Connector of the Main Central Processing

Unit (CPU) Board (see

Figure 1

on

page 7

).