START-UP AND TEST
INSTALLATION COMPLETION CHECKLIST
Review the information below to verify the proper installation of the Series 9820A dispensing unit.
If the installation does not meet criteria listed, correct the problem before the start-up is
performed.
1.
To avoid damage to the CPU PC board, verify that the SLOW FLOW and FAST FLOW
wires are not shorted to any conduit or chassis metal, mis-wired, or connected to any
equipment requiring more than stated maximum allowable current.
2.
The register and pumping unit must be properly secured.
3.
All plumbing must be complete and tight. All liquid-carrying lines must be checked for
leaks.
4. When DC pulse output lines are used in the pump for connecting to GASBOY fuel
management systems, the AC and DC wires must not share any conduits, junction boxes, or
troughs except as noted in Section 4, Wire Size.
5. All conduit work must be complete. All junction box covers must be secured. Conduits
should not be sealed until the wiring is verified through proper operation.
6.
The unit must be properly grounded.
7. Before any testing begins, remove any water in the tank through a fill opening, using a
suitable pump. Do not use the GASBOY pump to remove water. Serious damage may
occur.
8.
A sufficient volume of fuel must be put in the tank to insure that the liquid level is above the
bottom of the suction pipe.