beautypg.com

7 initial operation, Initial operation -9 – Daktronics AE-3010-7.6-R,G,A User Manual

Page 29

background image

Electrical Installation

3-9

1. Plug one end of the flipped RJ11 cable into the “Signal Out” output jack on the

first display and the other end of the cable in the input jack on the next display.

2. Refer to

Figure 25

.

3. Continue this procedure throughout the network. When the cabling is

complete, the last display will have nothing in the output jack.

3.7 Initial Operation

Each time power is applied to the display; the display will run through an
initialization in which it will display the following:

1. Output Test (DDDs)
2. Product Name (Galaxy)
3. Display Size (Row x Column)
4. Firmware Number (ED10134)
5. Firmware Revision (Rev X.XX)
6. COM1 Configuration (C1: V15/RTD)
7. COM2 Configuration (C2: None)
8. Line Frequency (60 Hz)
9. Hardware Address (HW: XX)
10. Software Address (SW: XX)
11. Display Name
12. Modem (if Present)