1 Rig with 4 cables and spread with two 95-in. (2413-mm) and

2 “A” long suitable spreader bars.

2 Center of gravity and unit weight include economizer, but not econ­

omizer hood

NOTES:

A CAUTION

1 All panels must be in place when rigging.
2. Unit is not designed for handling by forklift truck.

3/4 IN (19 MM) NOTCHES

IN END OF SPREADERS

NOTICE TO RIGGERS

MODEL

UNIT WEIGHT

A

B

C

Lb

Kg

In.

mm

In.

mm

In.

mm

48LJD

2895

1313

85 91

2182

61

1549

43

1092

49LJE

2975

1349

85.91

2182

61

1549

43

1092

50LJ

2565

1164

6.14

1680

49

1245

44

1118

50LW

2775

1259

85.91

2182

61

1549

43

1092

ACCESSORY/OPTION WEIGHTS

ROOF CURB

ECONOMIZER

WITHOUT HOOD

ECONOMIZER

HOOD

POWER EXHAUST/

BAROMETRIC
RELIEF HOOD

Lb

Kg

Lb

Kg

Lb

Kg

Lb

Kg

280

127

140

63.6

155

70.3

130

59.1

Fig. 1 — Rigging Labei

Field-Fabricated Ductwork

— Secure all ducts to

building structure, using flexible duct connectors between
roofcurb and ducts as required. Ducts passing through an
unconditioned space must be insulated and covered with a
vapor barrier. Outlet grilles must not lie directly below unit
discharge.
48LJ UNITS — These units are field-convertible with the
use of an accessory horizontal conversion kit. They are shipped
from the factory as vertical supply/retum, but may be field
converted to horizontal supply/retum.

Attach field-fabricated ductwork to the roof curb. The

retum-air duct connection (inside dimensions) is 46.75-in.
long X 30.59-in. wide; the supply-air duct connection (in­

side dimensions) is 38.63-in. long x 27-in. wide. Connect

ductwork to 16-gage roof curb material. Secure all ducts to
the building structure, using flexible duct connectors be­
tween roof curb and ducts as required. Ducts passing through
an unconditioned space must be insulated and covered with

a vapor barrier. Outlet grilles must not lie directly below
unit discharge. The return duct must have a 90-degree el­

bow before opening into the occupied building space if unit

is equipped with power exhaust.

Vertical discharge ducts are designed to be attached to

accessory roof curb. If unit is mounted on dunnage, it is
recommended that the ducts be supported by cross braces
as shown for accessory roof curb. Duct should be the same
size as shown on the roof curb certified drawing.

Units may be connected to horizontal supply/retum

ductwork with the use of the accessory horizontal conver­
sion package.

50LJ UNITS — On these units, attach field-fabricated
ductwork to roof curb. The retum-air duct connection
(inside dimensions) is 49.81-in. long x 30.59-in. wide; the
supply-air duct connection (inside dimensions) is 37.87-in.
long X 31.02-in. wide. Connect ductwork to 16-gage roof
curb material. (See installation instractions shipped with
accessory roof curb.)

50LW UNITS — On these units, attach field-fabricated
ductwork to factory-supplied duct flanges mounted on the
side of the unit. See Fig. 5c. Duct flange height is approx­
imately one inch; flange is 18-gage sheet metal. The hori­
zontal supply and return duct openings (inside dimensions)
are 26.85-in. wide x 42.03-in. high.