Series 8750XD Unitized Curtain Wall Installation Instructions

Section 15 - Deglaze / Re-glaze Procedures - SSG System

Figure 105

e. Apply temporary retainers at verticals. Temporary retainers will be comprised of FM38, 4” pieces of 17T2 and WC22 gasket. If there is captured

glazed system on the job used scraps for this. If there is none available then the materials for these temporary retainers must be ordered.

g. Tool the sealant around the perimeter of the glazing, packing the sealant into the joint, to ensure any voids or air bubbles in the sealant are

eliminated.

h. Once the structural silicone cures remove the temporary glazing retainers, and replace with LC45 with cover.
i.

Do not apply the weather seal around the perimeter of the glazing until the structural silicone joint cures. The SSG joint will typically take 7-14 days,
but it can take up to 28 days to fully cure depending on temperature and humidity. Consultation with the sealant manufacturer is recommended.

j.

When the structural silicone joints are fully cured, remove the temporary retainers. Properly clean and prepare the joints, apply backer rod and the
weather seal. Tool the joint to form an hour glass shaped sealant joint as shown.

4” Temporary
glazing
retainer at
jambs. Do
not remove
until sealant
at horizontals
has cured

Set the glazing

in place,

pressing the

glazing firmly

against the

spacer gaskets.

Figure 106

Figure 107

Do not apply the
exterior weather
seal until the
silicone has
cured.

After silicone

cures remove

temporary

glazing retainers

and replace with

LC45 and cover.