Series 8750XD Unitized Curtain Wall Installation Instructions

1. The deglaze and re-glaze procedure must be performed from a swing stage or man lift from the exterior of the building. Follow the sealant manufacture’s

sealant application instruction for deglazing and re-glazing. When deglazing an opening or openings at a structural silicone glazed unit follow these
instructions:

a. Cut and remove the weather seal, side blocks and setting blocks, from around the lite of glazing.
b. Using tools, such as automotive deglazing tools, cut though the glazing sealant removing glazing, old gasket and sealant from the opening. Some

areas may be accessible from the interior.

c. Cut away the sealant from the substrate, leaving a thin film (approximately 1/32” thick) of sealant on the frame. Do not damage the surface finish of

the substrate. Alternatively, if the remaining sealant exhibits adhesive failure, completely remove all sealant, but take care not to damage the
substrate finish.

d. Remove all remaining gasket pieces or sealant residue from inside the gasket reglets.
e. Remove LC45 and Cover from verticals.

Section 15 - Deglaze / Re-glaze Procedures - SSG System

Cut completely
through the sealant
joint and remove the
sealant and gaskets.

Remove LC45

and cover at

verticals only

Remove setting
and side blocks
from the opening of
lite to be deglazed.

Cut out and

remove the

weather

seals.

Cut completely

through the sealant

joint and remove the
sealant and gaskets.

Cut out and remove

the weather seals.

Figure 102

Remove setting
and side blocks
from the opening of
lite to be deglazed.

Figure 100

Figure 101