Section 15:deglaze/re-glaze procedures-ssg system – EFCO 8750XD User Manual
Page 41

EFCO 2012
Page 41
Series 8750XD Unitized Curtain Wall Installation Instructions
1. The deglaze and re-glaze procedure must be performed from a swing stage or man lift from the exterior of the building. Follow the sealant manufacture’s
sealant application instruction for deglazing and re-glazing. When deglazing an opening or openings at a structural silicone glazed unit follow these
instructions:
a. Cut and remove the weather seal, side blocks and setting blocks, from around the lite of glazing.
b. Using tools, such as automotive deglazing tools, cut though the glazing sealant removing glazing, old gasket and sealant from the opening. Some
areas may be accessible from the interior.
c. Cut away the sealant from the substrate, leaving a thin film (approximately 1/32” thick) of sealant on the frame. Do not damage the surface finish of
the substrate. Alternatively, if the remaining sealant exhibits adhesive failure, completely remove all sealant, but take care not to damage the
substrate finish.
d. Remove all remaining gasket pieces or sealant residue from inside the gasket reglets.
e. Remove LC45 and Cover from verticals.
Section 15 - Deglaze / Re-glaze Procedures - SSG System
Cut completely
through the sealant
joint and remove the
sealant and gaskets.
Remove LC45
and cover at
verticals only
Remove setting
and side blocks
from the opening of
lite to be deglazed.
Cut out and
remove the
weather
seals.
Cut completely
through the sealant
joint and remove the
sealant and gaskets.
Cut out and remove
the weather seals.
Figure 102
Remove setting
and side blocks
from the opening of
lite to be deglazed.
Figure 100
Figure 101