Subsill and Subhead Splicing Instruc ons 

 Splices should be located at appropriate loca ons 

to account for all expected thermal movement 
and/or aesthe c.   

 Splice joints are typically placed every 16 feet  

maximum with a 1/2” separa on. (Reference    
approved shop drawings for specifics of job) 

 Field apply 4” Perma‐Barrier tape (EFCO part # 

WM01) to the joints. 

 Field apply non‐hardening, skinning sealant over 

the tape at the joints. 

 Subsill Splicing: 



Apply 4” Perma‐Barrier tape (EFCO part # 
WM01) to underside of subsill joint. 



Apply sealant over the tape at the joints. 



Ensure that the sealant overlaps the    
aluminum surfaces by at least 1/8”. 

 Subhead Splicing: 



Apply 4” Perma‐Barrier tape (EFCO part # 
WM01) to inside of subhead joint star ng 
above gasket reglet and stopping at     
closure hook. 



Apply sealant over the tape at the joints. 



Ensure that the sealant overlaps the    
aluminum surfaces by at least 1/8”. 



Apply 4” Perma‐Barrier tape (EFCO part # 
WM01) to outside of subhead joint. 

 Closure splices should be at a different loca on 

than the subhead, using a similar Perma‐barrier 
and sealant applica on. 

Apply WM01 
to under side 
of Subsill 

Seal over tape 
at joint 

Apply WM01 
to under side 
of subhead 

Seal over tape 
at joint 

Apply WM01 
to top side of 
subhead 

Underside of subsill shown 

Top side of subsill shown 

Inside of subhead shown 

Outside of subhead shown 